One electrical power outage (PO) (See definition of Power Outage below) has
been scheduled for the following buildings (see Building list below).
The outage will be as follows:
Power Outage:
The Power Outage will start Saturday Feb 27th at 6:00 AM and continue for 12 hours ending on Saturday Feb 27th at 6:00 PM.
The reason for the outage is to install new HV cable for the New Dining Facility.
Definition: A Power Outage (PO) is described as any schedule event more than 1 hour.
This power outage consists of operating a 13.2KV distribution circuit breaker and turning power off to the complete or partial 13.2KV UT circuit.
Questions concerning this outage may be directed to Cesar Peņalba at 974-7769
[log in to unmask].
Building List:
Fred Brown Residence Hall
Magnolia Residence Hall
Dogwood Residence Hall
Orange Residence Hall
White Residence Hall
Reese Residence Hall
Laurel Residence Hall
Reese Chiller Bldg
Presidential Court (Aramark)
Parking Garage G7
Parking Garage G10 (East)
Student Aquatic Center
Student Recreational and Fitness Center (TRECS)
Transportation Services (Fleet Management)
Old Facilities Services buildings (A&A and Eng areas) New Parking Lot (Bubble old site)
Tom Black Track and Press Box
North and South Carrick
Fire Pump House - Carrick