One electrical power outage (PO) (See definition of Power Outage) has been scheduled for the following buildings (see Building list below). The outage will be as follows:
Power Outage
The Power Outage will start Friday June 29th, at 9:00 PM and continue for 6 hours, ending on Saturday, June 30th at 3:00 AM.
The reason for the outage is to connect new 15KV service to the West Campus Redevelopment (Buildings 3 and 6).
Note:
Outage Safety meeting will be held on Friday, June 29th at 8:00 PM at the Christman's Construction Trailer.
Definition: A Power Outage (PO) is described as any schedule event greater than 1 hour.
This power outage consists of operating a 13.2KV distribution circuit breaker and turning power off to the complete or partial 13.2KV UT circuit.
Questions concerning this outage may be directed to Roy Warwick at 974- 7768 [log in to unmask] or Cesar Peņalba at 974-7769 [log in to unmask]
Buildings List
Fred Brown Residence Hall
Laurel Residence Hall
Orange Residence Hall
White Residence Hall
Reese Residence Hall
Reese Chiller Building
WCR Building 3 and 6 Temp Construction Power
Presidential Court (Aramark)
Parking Garage G7
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
To join/leave the list or browse past event notifications, please see
http://listserv.utk.edu/archives/oitevents.html
For information and support, please contact:
OIT HelpDesk (865) 974-9900
|