Two (2) building switching electrical power outages (PO) (See definition of Building Switching Power Outage) have been scheduled for Kingston Pike Building. The outages will be as follows:
Switching Power Outage #1
The switching Power Outage will start Monday, November 27th at 9:00 am and continue for 5 minutes ending on Monday November 27th , 9:05 am
The reason for the outage is to perform emergency generator test for OIT UPS.
Switching Power Outage #2
The switching Power Outage will start Monday, November 27th at11:00 am and continue for 5 minutes ending on Monday November 27th , 11:05 am
The reason for the outage is to remove emergency generator power and return building to utility power.
Pre-outage UT Safety Meeting is scheduled for 8:45am at KPB, EPP Rm
Definition: A Building Switching Power Outage (PO) is described as switching off the main service transformer or main service disconnect of the building for a period of time less than 1 hour.
Questions concerning this outage may be directed to Cesar Penalba at 974-7769 [log in to unmask]
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-