One electrical power outage (PO) (See definition of Power Outage) has been scheduled for the following buildings (see Building list below). The outage will be as follows:
Power Outage
The Power Outage will start Thursday, May 18th 6:00 pm and continue for 4 hours ending on Thursday May 18th, 10:00 pm
The reason for the outage is to support the West Campus Redevelopment Project, specifically the demolition of Humes Hall, connected to Circuit 1 and its stand-by circuit 2.
Definition: A Power Outage (PO) is described as any schedule event greater than 2 hours .
This power outage consists of operating a 13.2KV distribution circuit breaker turning power off to the complete UT circuit 1 and Circuit 2.
Questions concerning this outage may be directed to Roy Warwick at 974- 7768 [log in to unmask] or Cesar Peņalba at 974-7769 cpenalb1@ut k.edu.
Buildings List
Student Aquatic Center
Sports Bubble
Morrill Hall
Carrick Hall North
Carrick Hall South
Reese Hall
Reese Hall Chiller
Presidential Court
Health, Physical Education and Recreation Building (HPER)
Tennessee Recreation Center for Students(T-RECS)
Fleet Management
UT Drive Services Building A
UT Drive Services Building B
UT Drive Services Building C
West Campus Parking Garage G-7
Tom Black Track
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
To join/leave the list or browse past event notifications, please see
http://listserv.utk.edu/archives/oitevents.html
For information and support, please contact:
OIT HelpDesk (865) 974-9900
|