One (1) electrical power outages (PO) has been scheduled for the Student Union Phase I. The outage will be as follows:
Power Outage
The Power Outage will start Monday, May 15th 7:00 am and continue for 48 hours ending on Wednesday, May 17th 7:00 am
The reason for the outage is to support the contractor in the connection of a new 2500KVA transformer (HV and LV) to Phase I and install 3750KVA transformer in Phase II.
Lastly a new HV 13.2KV Vista Switch for Student Union Phase I and 2 will be energized.
Questions concerning this outage may be directed to Roy Warwick at 974- 7768 [log in to unmask] or Cesar Peņalba at 974-7769 cpenalb1@ut k.edu.
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-