Four (4) electrical switching power outages (SPO) (See definition of Switching Power Outage) have been scheduled.
The switching power outages will be as follows:
Switching Power Outage 1 of 4
Outage will start Thursday, Aug 11th 2016 at 10:45pm . Buildings affected:
Stokely Management Center
Haslam Business
Switching Power Outage 2 of 4
Outage will start Thursday, Aug 11th 2016 at 10:55pm . Buildings affected:
Humanities
Humanities Parking Garage
McClung Tower and Plaza
Switching Power Outage 3 of 4
Outage will start Friday, Aug 12th 2016 at 3:15am . Buildings affected:
Stokely Management Center
Haslam Business
Switching Power Outage 4 of 4
Outage will start Friday, Aug 12th 2016 at 3:25am . Buildings affected:
Humanities
Humanities Parking Garage
McClung Tower and Plaza
The reason for the outage is for Electrical Services to perform emergency maintenance work at our main UT 13.2KV substation overhead structure. (UTK circuits 3,4,5,6)
Definition: A Switching Power Outage (SPO) is described as any schedule event less than 5 minutes. The switching power outage consists of operating 13.2KV switches at one building. This operation is open transition from a Normal source to Standby source or vice versa.
Questions concerning this outage may be directed to Cesar Penalba at 974-7769 [log in to unmask]
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
To join/leave the list or browse past event notifications, please see
http://listserv.utk.edu/archives/oitevents.html
For information and support, please contact:
OIT HelpDesk (865) 974-9900
|