Two (2) electrical power outages (PO) (See definition of Power Outage) have been scheduled for the following buildings (see attached Building list). The outage will begin as follows:
Power Outage No.1:
The Power Outage will start Friday. June 26th at 6:00 pm and continue for 2 hours ending on Friday. June 26th at 8: 00 pm
Power Outage No.2:
The Power Outage will start Sunday. June 28th at 2:00 pm and continue for 2 hours ending on Sunday. June 28th at4:00 pm
The reason for the outage is to replace [2] 1000KVA 13.2KV to 480V transformers at Communications' East and West Chiller building.
Definition: A Power Outage (PO) is described as any schedule event greater than 2 hours.
This power outage consists of operating a 13.2KV circuit switch at the main substation. (Circuit Outage)
Questions concerning this outage may be directed to Roy Warwick at 974- 7768 [log in to unmask] or Cesar Peņalba at 974-7769 [log in to unmask] .
Buildings List
Administration Parking Garage Andy Holt Tower
Berry Hall
College of Nursing
East Skybox & Pressbox
Estabrook Hall
Hearing and Speech Center
Jane and David Baily Education Complex
John D. Tickle Engineering Building
Neyland Drive Biology Annex
Pasqua Nuclear Engineering Building
Pratt Pavilion
South & East Stadium
Stadium Drive Parking Garage G-10
Steam Plant
Steam Plant Coal Conveyor Shed
Steam Plant Gear Switching/Turbine Building
Student Services Building
Thompson-Boling Assembly Center
West Skybox Addition
New Gibbs (Under construction-Blaine)
New Parking Garage (Under construction-Blaine)
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
To join/leave the list or browse past event notifications, please see
http://listserv.utk.edu/archives/oitevents.html
For information and support, please contact:
OIT HelpDesk (865) 974-9900
|
|
|
|
|
|