One (1) electrical power outage (PO) (See definition of Power Outage) and HVAC outage have been scheduled for the following buildings (see Building list below). The outage will begin as follows:
The Power Outage will start Friday, July 31 at 6:00 pm and continue for 46 hours ending on Sunday, August 2nd at 4:00 pm
The reason for the outage is to replace existing 1500KVA building transformer with a new one (Humanities basement- Incinerator Room).
This transformer feeds the HVAC equipment for Humanities and McClung Tower.
Definition: A Power Outage (PO) is described as any scheduled event greater than 2 hours.
This power outage consists of operating a 13.2KV building switch at the building's HV switchgear room.
Questions concerning this outage may be directed to Roy Warwick at 974- 7768 [log in to unmask] or Cesar Peņalba at 974-7769 [log in to unmask]
Buildings List
Humanities -Basement - Electrical outage
Humanities -Building - HVAC outage
McClung Tower -Building -HVAC outage
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-