One (1) electrical power outage (PO) (See definition of Power Outage) and (1) HVAC outage have been scheduled for the following buildings (see list below).
The outage will begin as follows:
The Power Outage will start Friday, August 7th at 6:00 pm and continue for 46 hours ending on Sunday, August 9th at 4:00 pm
The reason for the outage is to replace existing 1500KVA building transformer with a new one (Humanities basement- Incinerator Rm.).
This transformer feeds the HVAC equipment for Humanities and McClung Tower.
Definition: A Power Outage (PO) is described as any schedule event greater than 2 hours.
This power outage consists of operating a 13.2KV building switch at the building's HV switchgear room.
Questions concerning this outage may be directed to Roy Warwick at 974- 7768 [log in to unmask] or Cesar Peņalba at 974-7769
[log in to unmask] .
Buildings List
Humanities and Social Sciences Building
McClung Tower - HVAC outage only
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
To join/leave the list or browse past event notifications, please see
http://listserv.utk.edu/archives/oitevents.html
For information and support, please contact:
OIT HelpDesk (865) 974-9900
|
|
|
|
|
|