One (1) electrical power outage (PO) (See definition of Power Outage) has been scheduled for Humanities and Social Sciences.
The outage will begin as follows:
The Power Outage will start Friday, May 29th at 6:00 pm and continue for 46 hours ending on Sunday, May 31th at 4:00pm
The reason for the outage is to replace Humanities' Mechanical Room (Incinerator Room) main 13.2KV switch, and 1500KVA transformer.
Definition: A Power Outage (PO) is described as any scheduled event greater than 4 hours.
This power outage consists of operating a 13.2KV switch at the building.
This operation turns power off to 1 of 3 substations of the building.
Questions concerning this outage may be directed to Roy Warwick at 974- 7768 [log in to unmask] or Cesar Penalba at 974-7769 [log in to unmask] .
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-