Two (2) electrical switching power outages (PO) (See definition of Switching Power Outage) have been scheduled for the following buildings (see Building list below).
The outages will begin as follows:
Switching Power Outage No. 1 will begin on Saturday, June 28th, 7:00am and will continue for one (1) hour ending on Saturday, June 28th, 8:00am
The purpose of this outage is to temporarily switch the 13.2KV electrical feed from Normal supply (CKT # LA3) to Stand-by (Ckt 2) to install new 15KV cable for the UC project.
Switching Power Outage No. 2 will begin on , Saturday June 28th, 11:30pm and will continue for one (1) hour ending on Sunday, June 29th, 12:30 am.
The purpose of this outage is to permanently switch the 13.2KV electrical feed from Stand-by (Ckt 2) back to their Normal source.
Definition: Switching Power Outage (PO) - 1 hour
The power outage consists of operating a 13.2KV switch at the incoming building service. This operation turns power off to each individual building,
Questions concerning this outage may be directed to Roy Warwick at 974-7768 [log in to unmask] or Cesar Penalba 974-7769 [log in to unmask] .
Buildings List
Alumni Memorial Building
Austin Peay Building
Burchfiel Geography Building
Dougherty Engineering Building
Earth and Planetary Sciences Building
Ferris Hall
Hesler Biology Building and Greenhouse
Nielsen Physics Building
Perkins Hall
Walters Life Sciences Building
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-