An electrical power outage (PO) (See definition of power outage) has been scheduled for the buildings listed below.
The outage will begin on Saturday, March 31, 2012 at 1:00 am and will end on Saturday March 31, 2012 at 7:00 am.
The purpose of this outage is to install new 15KV cable in underground distribution for the New Laurel Substation project.
Definition: Power Outage (PO) - 6 hours
The power outage consists of operating a 13.2KV switch at the SUBSTATION.
This operation turns power off to the complete circuit (all buildings attached to the circuit).
Questions concerning this outage may be directed to Roy Warwick at 974-2415 or [log in to unmask]
Buildings List
Alumni Memorial Building
Austin Peay Building
Burchfiel Geography Building
Dougherty Engineering Building
Earth and Planetary Sciences Building
Ferris Hall
Hesler Biology Building and Greenhouse
Nielsen Physics Building
North Neyland Stadium
Perkins Hall
Walters Life Sciences Building
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
To join/leave the list or browse past event notifications, please see
http://listserv.utk.edu/archives/oitevents.html
For information and support, please contact:
OIT HelpDesk (865) 974-9900
|
|
|
|
|
|