An electrical power outage (PO) (See definition of power outage) has been scheduled for the following buildings listed below.
The outage will begin on Sunday, March 18, 2012 at 3:00 pm and will end on Sunday March 18, 2012 at 8:00 pm.
The purpose of this outage is to install new 15KV cable in underground distribution for the New Laurel Substation project.
Definition: Power Outage (PO) - 4-6 hours
The power outage consists of operating a 13.2KV switch at the SUBSTATION.
This operation turns power off to the complete circuit (all buildings attached
to the circuit).
Questions concerning this outage may be directed to Roy Warwick at 974-2415 or [log in to unmask]
Buildings List
11th Street Parking Garage
Blount Hall
Carriage House
Early Learning Center - Research & Practices
Hoskins Library Chiller Building
James D. Hoskins Library
Jessie W. Harris Building
Law Complex: George C. Taylor Wing
Law Complex: Law Library and Classrooms
Panhellenic Building
Senter Hall
Tandec - Textiles and Nonwovens Development
Frank G. Clement Hall
Sophronia Strong Hall and Cafeteria
White Avenue Parking Garage
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
To join/leave the list or browse past event notifications, please see
http://listserv.utk.edu/archives/oitevents.html
For information and support, please contact:
OIT HelpDesk (865) 974-9900
|
|
|
|
|
|